Civil engineering · Construction · Inspection

A fictional civil project example

One question. A traceable next step.

RFI-007 concerns a storm-drain crossing with different elevations shown on two project drawings. This example demonstrates a documentation workflow, not a real project decision.

Project and location
Fictional Cedar Creek drainage renewal · Station 12+40
Source documents
Drainage plan C-102 revision B and utility profile C-501 revision A
Observed discrepancy
The documents show different elevations at the same crossing.
Question
Please clarify the governing elevation and provide the authorized written response and reference.
Current status
Open — awaiting the designated reviewer's written response.
After a response
Record its source, revision, distribution, and any separate change-review requirement.

A recorded question or verbal comment does not authorize a change to the work.