A fictional civil project example
One question. A traceable next step.
RFI-007 concerns a storm-drain crossing with different elevations shown on two project drawings. This example demonstrates a documentation workflow, not a real project decision.
- Project and location
- Fictional Cedar Creek drainage renewal · Station 12+40
- Source documents
- Drainage plan C-102 revision B and utility profile C-501 revision A
- Observed discrepancy
- The documents show different elevations at the same crossing.
- Question
- Please clarify the governing elevation and provide the authorized written response and reference.
- Current status
- Open — awaiting the designated reviewer's written response.
- After a response
- Record its source, revision, distribution, and any separate change-review requirement.
A recorded question or verbal comment does not authorize a change to the work.